Pustaka Negeri Sarawak, Sibu
Pustaka Negeri Sarawak, Sibu is the latest addition to the existing campuses besides Kuching, Miri and SRR.
Project Description
Project Particulars :
- Letter of Acceptance : 28 .10.2016
- Date of Commencement : 25.11.2016
- Contract Period : Twenty four (24) months
- Date of Completion : 24.11.2018
- Revised Completion Date :
- EOT No.1=27 days, 21 December 2018, Reason:EIW
- EOT No.2=210 days, 19 July 2019, Reason:lift design change
- Expected completion date : 31 January 2020 (delay 196 days from EOT 2)
- Contract Sum : RM 30,768,126.84
- Contractor : Woodville Jaya Sdn. Bhd.
- Project Director : Regional Manager, Central Regional Office, JKR SARAWAK
History
Construction of Sibu Library is a node of the Sarawak State Library (Pustaka) in the central zone of Sarawak. It is in line with SITRC Meeting No.1 / 2002 dated 27 February 2002 stating that "Regional Centers for Pustaka will be located in Sibu and Miri". The project is also in line with the aspirations and policies of the Sarawak State Government to set up information centers in major cities in the state.
The project is a direct negotiated contract and started in 2001 with an initial grant of RM300,000. Since then many discussions have been made to determine the concept of the library. In 2005 the Land and Survey Department approved Lot 456, Block 1, Sungai Merah Town District, Sibu as the project site. From 2006 to 2010 the project was dismissed as there was no provision.
In spite of this, in 2011, the Public Works Department was directed by the Ministry of Infrastructure and Communications Development to re-implement the Sibu Library project with ceiling cost of RM25,000,000. In the same year, the Department of Land and Surveys had extended the tenure of placement at Lot 456, Block 1, Sungai Merah Town District, Sibu for two (2) years starting April 12, 2011. From 2011 to 2012, the project allocation of RM15,000,000 has been transferred to the Library account to finance project implementation.
In 2013, the original site of the project at Lot 456, Block 1, Sungai Merah Town District, Sibu was canceled and replaced with Lot 1054 in the same district. The site change took place again in 2014, where Lot 1054 was canceled and replaced with Lot 1607. The exchange of this project site requires the Library and the Public Works Department to submit a building plan and site plan to the appropriate authority for approval. This sequence of events is a major factor that has caused delays in the implementation of the Sibu Library project.
As of 25th February 2020, the actual progress was 92.68% against the scheduled which was 100%.Before the enforcement of movement control order (MCO) for Covid-19 MCO, the office area of Pustaka Sibu supposed to be ready on 16 March 2020 while the inspection for Certificate Practical Completion (CPC) was scheduled on 1st April 2020. Also, Pustaka Sibu was expected to open its services to the public by 1st June 2020 while the grand launching was further delayed from 23rd April 2020 to 9 September 2020 due to unavailability of Sarawak's Chief Minister.
Staff Movement from Kuching to Sibu
On 3 February 2020, the first batch of Pustaka Sibu's staff arrived in Sibu and set up their temporary working site at Sibu Municipal Council Library (SMC Library). All staff, except for the Technical Services Division present on that day. The first briefing was also held on that day to commemorate their first working day in Sibu. They were led by Regional Manager Sibu, Fairul Azli Banchit.
Staff
-
Batch 1 : January 2018
- Afiza binti Ibrahim
- Heliza Binti Rapaie
- Muhammad Aufa Bin Mohamad Jamaludin
- Suhaimi Bemban
- Dzairil Erwan bin Sapar
- Fairul Azli Banchit
- Muhamad Ali Bin Abdul Wahab
- Nurfarathul Aqma Julani
- Nur Faziella Syazmeen binti Hasli
- Fiona Ravia
- Nur Amanina Mastani
- Mohd Feizul Bin Median
- Nurrul Azzila Binti Abdul Rasid
- Shahrieza Binti Rabaie
- Mohd Tarmizi bin Malek
- Mohd Asraf Bin Abdul Wahab
- Ebby Saifullah bin Suhaimi
- Fatin Fahsa binti Adenan
- Aida Suraya Yaseer binti Samson
- Mas Azreena binti Majenis
- Safwan Hanif bin Osman
- Sofea binti Sharif
- Siti Nurhafizah binti Sajeli@Sejali
- Annasyah binti Hajemi
- Norzieana binti Mohammad Nasir
- Mohamad Nazrin bin Mohamad Junaidi (resigned on 15 Feb 2020 and join SEB)
- Nur Syahida Binti Ispawi
- Bibiana Nain Anak Ugop
- Faeza Hanim binti Morshidi
- Mohammad Noor Idzhwan bin Sarkawi
Batch 2 : July 2018
Batch 3 : September 2018
Batch 4 : November 2018 (New intake)
Batch 5 : February 2019 (New intake)
Batch 6 : November 2019 (New intake)
Divisions
a) Corporate Management Division, Sibu
b) Information Services Division, Sibu
c) Technical Services Division, Sibu